.... that was the plan anyway, 16 September at Oulton Park.
Jobs that had to be done that would take time were :-
- Remove, paint & refit front and rear clams, bonnet and boot lids, roof and wing mirrors.
 - Full geo set up.
 - Fit Tillet race seat, fit drivers 6 point Schroth race harness, pax seat and Schroth 4 point harness.
 - Fit Lifeline electronic fire extinguisher, pipework and nozzles in cockpit and engine bay
 - Fit TSL timing unit
 - Fix faulty engine temp readout on stack dash
 - Test and fix lighting system and sort out rear fog light not working
 - Fit wheel arch liners
 - Find and fit door seals and fit doors properly!
 - Make and fit boot bulkhead
 - Fit graphics and series stickers
 
............. then I had to get some circuit time to learn to drive the car !!
To make matters worse, work was really busy and becoming a real time and thought distraction. The pressure of getting all the jobs done in time for Oulton was making the task just impossible... so I made the decision to pull out of Oulton. That would give me plenty of time, almost a month, before the next round that I could do which was Silverstone National on 16 October.
.... that seemed much more do-able! So the email went off to Mr Golding to say that I was scratching from Oulton. To say I was disappointed is an understatement but I was at the same time relieved as the pressure was off for a bit.